Runway 4R Updates

  • 9/14/09-9/18/09
  • Began hydroexcavation and pre-construction surveying work.  
  • Located exisitng utilities.
  • 09/21/09-09/25/09
  • Hydroexcavation of job perimeter
  • 10/05/09-10/09/09
  • Continued hydroexcavation
  • Restaked saw cut and updated utility asbuilt
  • 10/19/09-10/23/09
  • Graded stone lifts
  • 10/26/09-10/30/09
  • Fine graded stone lift
  • Started paving asphalt pad
  • 11/02/09-11/06/09
  • Staked delineators, light cans, and swale.
  • 11/09/09-11/13/09
  • Grading work and light can installation.