- 47th Street Intermodal Yard
4/21/08 - 4/25/08
- Pre-construction layout of high points and catch basins
5/12/08-5/16/08
- Removed trench drains on both pads
5/19/08-5/23/08
5/26/08-5/30/08
- Installed leveling binder on both pads, paved pad West of Pad track #12
6/02/08-6/06/08
- Completion of paving on the loading pad east of track #11.
6/30/08-7/04/08
- Installed new catch basins near 51st Street bridge
9/08/08-9/12/08
- Staked conduit runs on outbound gate at 51st street
9/15/08-9/19/08
- Began construction on outbound gate at 51st street
9/22/08-9/26/08
- Electricians continue laying conduit near 51st Street for the outbound gate
9/29/08-10/03/08
- Continued work on Outbound gate at 51st Street
- Electricians completed conduit runs from new camera pole base to the
bobtail lane
- Kiosk terminal base poured
- 4 handholes installed
10/13/08-10/17/08
- Electricians working on inbound gate
11/17/08-11/21/08
- Installation of new catch basins along outbound gate
11/24/08-11/28/08
- Finished installing 4 new catch basins and 30" sewer along new outbound
gate
- Began placing binder in outbound bobtail lane
12/01/08-12/05/08
- 47th street outbound gate current plans are now dated 9/19/08
- Preparation for concrete pouring at new outbound lane
12/08/08-12/12/08
- Cleanup from last week's work, new concrete curing
09/13/10-9/17/10
- Staked new location of Sand and Fuel Tracks North of 51st Street.
11/08/10-11/12/10
- Worked with NS track crews on tracks 17-29 at the South end of 51st Street
Yard