• 47th Street Intermodal Yard

4/21/08 - 4/25/08
  • Pre-construction layout of high points and catch basins

5/12/08-5/16/08
  • Removed trench drains on both pads

5/19/08-5/23/08
  • Grinding on both pads

5/26/08-5/30/08
  • Installed leveling binder on both pads, paved pad West of Pad track #12

6/02/08-6/06/08
  • Completion of paving on the loading pad east of track #11.

6/30/08-7/04/08
  • Installed new catch basins near 51st Street bridge

9/08/08-9/12/08
  • Staked conduit runs on outbound gate at 51st street

9/15/08-9/19/08
  • Began construction on outbound gate at 51st street

9/22/08-9/26/08
  • Electricians continue laying conduit near 51st Street for the outbound gate

9/29/08-10/03/08
  • Continued work on Outbound gate at 51st Street
  • Electricians completed conduit runs from new camera pole base to the
    bobtail lane
  • Kiosk terminal base poured
  • 4 handholes installed

10/13/08-10/17/08
  • Electricians working on inbound gate

11/17/08-11/21/08
  • Installation of new catch basins along outbound gate

11/24/08-11/28/08
  • Finished installing 4 new catch basins and 30" sewer along new outbound
    gate
  • Began placing binder in outbound bobtail lane
12/01/08-12/05/08
  • 47th street outbound gate current plans are now dated 9/19/08
  • Preparation for concrete pouring at new outbound lane
12/08/08-12/12/08
  • Cleanup from last week's work, new concrete curing
09/13/10-9/17/10
  • Staked new location of Sand and Fuel Tracks North of 51st Street.
11/08/10-11/12/10
  • Worked with NS track crews on tracks 17-29 at the South end of 51st Street
    Yard