Browning Engineering Limited
Ashland Yard
02/11/08-02/15/08
- Preconstruction Preparation and Staking of Silt Fence
3/24/08-3/28/08
- excavating and placing silk fence property line between Racine
and Morgan.
03/31/08-04/04/08
- Photographed site from Morgan to Racine.
- Dyer construction added ca6 and what you see is the finished
sub-grade
4/21/08 to 4/25/08
- Completed sub-ballast and berm East of Morgan Avenue
- Completed sub-ballast and berm between Racine and Morgan
Avenues.
- Dyer Construction began excavation of the 6 lead
- New pavement at Racine and Morgan Avenues completed
5/19/08 to 5/23/08
- Dyer Construction removed stone from 225+00 to 230+00
- Browning Engineering staked centerline of proposed CJ2
- Preconstruction meeting for track work
6/09/08-6/13/08
6/16/08-6/20/08
- Staked proposed CJ2 & Cj3 tracks
6/23/08-6/27/08
- Added topsoil and seeding to berms, began constructing CJ2
track East of Morgan
7/22/08-7/26/08
- Continued work on proposed CJ2 track
7/22/08-08/01/08
- Contractors continued building CJ2 track West of Racine Avenue
08/04/08-08/08/08
- Continued construction of CJ2
- Realignment of Iron Street Lead
08/11/15-08/15/08
- Construction of CJ2 through the crossing at Racine Avenue
09/02/08-09/05/08
- Completed cut & throw of new CJ2 track to old CJ2 track
- Started realignment of old CJ3 on East end of project
09/15/08-09/19/08
- Staked out proposed 6 Lead track
10/13/08-10/17/08
- Addition of future track at Racine and Morgan Avenue crossings