Browning Engineering Limited
Ashland Yard

02/11/08-02/15/08
  • Preconstruction Preparation and Staking of Silt Fence
3/24/08-3/28/08
  • excavating and placing silk fence property line between Racine
    and Morgan.
03/31/08-04/04/08
  • Photographed site from Morgan to Racine.  
  • Dyer construction added ca6 and what you see is the finished
    sub-grade
4/21/08 to 4/25/08
  • Completed sub-ballast and berm East of Morgan Avenue
  • Completed sub-ballast and berm between Racine and Morgan
    Avenues.
  • Dyer Construction began excavation of the 6 lead
  • New pavement at Racine and Morgan Avenues completed
5/19/08 to 5/23/08
  • Dyer Construction removed stone from 225+00 to 230+00
  • Browning Engineering staked centerline of proposed CJ2
  • Preconstruction meeting for track work
6/09/08-6/13/08
  • Surveyed Vanek Property
6/16/08-6/20/08
  • Staked proposed CJ2 & Cj3 tracks
6/23/08-6/27/08
  • Added topsoil and seeding to berms, began constructing CJ2
    track East of Morgan
7/22/08-7/26/08
  • Continued work on proposed CJ2 track
7/22/08-08/01/08
  • Contractors continued building CJ2 track West of Racine Avenue
08/04/08-08/08/08
  • Continued construction of CJ2
  • Realignment of Iron Street Lead
08/11/15-08/15/08
  • Construction of CJ2 through the crossing at Racine Avenue
09/02/08-09/05/08
  • Completed cut & throw of new CJ2 track to old CJ2 track
  • Started realignment of old CJ3 on East end of project
09/15/08-09/19/08
  • Staked out proposed 6 Lead track
10/13/08-10/17/08
  • Addition of future track at Racine and Morgan Avenue crossings