• January 28-February 1st
  • Working on State Street and 63 rd Street Bridges
  • February 11-February 15th
  • Working on State Street and 63 rd Street Bridges
  • July 14- July 18
  • Staked underground North of 63rd Street bridge on proposed pad #2
  • July 22- July 26
  • Begin installation of new underground structures north of the 63rd street bridge
  • July 28-August 1st
  • Continued installation of underground structures north of the 63rd Street Bridge
  • Staked light towers
  • Staked underground structures between the bridges
  • August 04-August 08
  • K-five grinds for track 5
  • August 11-August 15
  • Reliable removes old underground structures and installs new structures over the
    area of proposed pad #2
  • Reliable begins installation of catch basins between bridges
  • Aldridge begins work on relocating light towers
  • September 02-September 5
  • Staking and trimming of Lane 5 for upcoming concrete pour
  • September 8-September 12
  • Poured concrete on Lane 5
  • September 15-September 19
  • Staked centerline for trimming.
  • Staked Lane 7 on 4' offset
  • K-five poured Lane 6
  • September 28-October 03
  • Poured concrete on Lane 7
  • October 06-October 10
  • Current plans revised 5/04/08
  • Staked & graded Lane 8
  • Staked centerline of track 6 from 341+00 to 346+50
  • October 13-October 17
  • Preparation of Lane 8 for concrete
  • October 27-October 31
  • Preparation of Lane 8 for pouring
  • Staked Track 5 from South end of new pad to match point
  • November 10- November 14
  • Poured concrete on Lane 8
  • November 17- November 21
  • Finished concrete around structures in center of new pad
  • Worked on drainage near 61st Street
  • November 24-November 28
  • Staked centerline of tracks 5 & 6 North of loading pad 2 for upcoming grinding work
  • December 01-December 05
  • K-Five finished excavation and stone for proposed tracks 5&6 from the North end of the
                 new pad to 345+00
  • December 08-December 12
  • NS track crew began laying railroad ties in track 5 roadbed
  • Reliable to install air risers at proposed crossings for tracks 4,5&6
  • December 15- December 19
  • NS track crew begins building track 5 along new pad