• Taxiway WT  


6/02/08-6/06/08
  • Grinding of pavement and pavement removal of existing
    taxiway GG from runway 14L-32R North the runway 4L-22R.

6/09/08-6/13/08
  • Removal of stone and concrete on Phase 1
  • Installation of silt fence & snow fence.

6/16/08-6/20/08
  • Grinding for phase III
  • Installation of stone on Phase I

6/23/08-6/27/08
NOTE: Current plans dated 3-05-08
  • Completion of all asphalt in Phase 1
  • Began setting concrete forms in phase 1
  • Removal of old concrete and asphalt in Phase 3
  • Preparation of joint plan for phase 3
  • Began under-drain work in Phase 3

7/14/08-7/18/08
  • Installation of underdrain on Phase III
  • Preparation of subgrade for upcoming paving in Phase III

7/28/08-8/01/08
  • Completed asphalt lifts in Phase III
  • Set Light cans in Phase 1

8/28/08-9/01/08
  • Asbuilt of completed work in phases 1 & 3

9/08/08-9/12/08
  • Sodding and hydroseeding of new taxiway areas

9/22/08-9/26/08
  • Continued sodding of phases 1 & 3