6/02/08-6/06/08
- Grinding of pavement and pavement removal of existing
taxiway GG from runway 14L-32R North the runway 4L-22R.
6/09/08-6/13/08
- Removal of stone and concrete on Phase 1
- Installation of silt fence & snow fence.
6/16/08-6/20/08
- Grinding for phase III
- Installation of stone on Phase I
6/23/08-6/27/08
NOTE: Current plans dated 3-05-08
- Completion of all asphalt in Phase 1
- Began setting concrete forms in phase 1
- Removal of old concrete and asphalt in Phase 3
- Preparation of joint plan for phase 3
- Began under-drain work in Phase 3
7/14/08-7/18/08
- Installation of underdrain on Phase III
- Preparation of subgrade for upcoming paving in Phase III
7/28/08-8/01/08
- Completed asphalt lifts in Phase III
- Set Light cans in Phase 1
8/28/08-9/01/08
- Asbuilt of completed work in phases 1 & 3
9/08/08-9/12/08
- Sodding and hydroseeding of new taxiway areas
9/22/08-9/26/08
- Continued sodding of phases 1 & 3
Browning Engineering Limited