Ashland Grading Project

  • 5/23/11-5/27/11
  • Installed security fence inside Vanek property.  
  • Began grading work
  • 5/30/11-6/03/11
  • IFI completed security fence across Vanek property
  • Vulcan works on moving concrete pile
  • Dyer clears site and begins excavation in front of Vanek
    property
  • 6/06/11-6/10/11
  • Graded road and ditch from 215+00 to 221+00
  • C&S department relocated cables
  • 6/13/11-6/17/11
  • C&S completes cable relocation
  • Dyer resumes grading
  • 6/20/11-6/24/11
  • Dyer completes grading from 206+00 to 221+00
  • Track crew begins laying ties and rail from 200+00 to 212+00
  • 8/2911-9/02/11
  • Began sewer construction West of Racine Avenue
  • 9/05/11-9/09/11
  • Installed catch basins 3 thorugh 9 East of Racine Avenue
  • Began grading work inside Vulcan plant
  • 9/12/11-9/16/11
  • Completed grading inside Vulcan plant
  • 9/19/11-9/23/11
  • Completed grading outside of Vulcan plant along future CJ2
    roadbed.  
  • Completed fence removal.  
  • Vulcan set temporary fence.
  • 9/26/11-9/30/11
  • Track crew begins setting ties for new CJ2, security fence
    construction begins on West side of Vulcan plant
  • 01/23/12-1/27/12
  • Finishing sewer installation
Browning Engineering Limited