Browning Engineering Limited
Bedford Park

4/21/08 - 4/25/08
  • Worked on temporary connection between existing 7 lead and the new
    industrial track
  • Excavation on proposed 8 lead from 28+00 to 50+005/12-5/16: Staked
    underground
5/19/08-5/23/08
  • Staked underdrain and detention pond
5/26/08-5/30/08
  • Staked workpoints under Cicero avenue Bridge
6/23/08-6/27/08
  • Staked centerline of 8 Lead and Pocket track from Central Avenue to
    3+00        
7/07/08-7/11/08
  • Staked edge of stone for 8 Lead
7/15/08-7/19/08
  • Revised plans dated 7-11-2008
  • Staked edge of stone for proposed 8 lead from 3+50 to 48+50
  • Staked centerline of yard tracks 1 & 2 and the proposed pocket track.
7/28/08-8/01/08
  • Continued staking switches and frogs at the West end of the project
  • Began layout of the proposed 8 Lead track East of Central Avenue
8/04/08-8/08/08
  • Staked yard tracks 1 & 2
  • Continued staking proposed 8 Lead
08/11/08-08/18-08
  • Construction of 8 Lead from Central avenue to sta. 20+00
  • Removal of service road to make room for 7 & 8 Leads near sta. 48+00
08/18/08-08/22/08
  • Staked retaining wall, 7 & 8 Leads near Cicero Avenue Bridge
  • Continued construction of 8 Lead East of Central
08/25/08-8/29/08
  • Continued excavation of 7 & 8 leads just West of Cicero Avenue Bridge
  • Preparation of 7 Lead from 0+00 to 7+00
9/02/08-9/05/08
  • Excavation for retaining wall
  • Staking of 7 & 8 Leads under Cicero Avenue bridge
9/08/08-9/12/08
  • Staked retaining wall
9/15/08-9/19/08
  • Staked 6 Lead realignment on West end of site
  • Staked temporary connection track between 6 & 8 leads
  • Staked realignment of 8A Lead
9/22/08-9/26/08
  • Staked 7 & 8 Leads near 8A Lead
  • Staked Cicero Avenue Bridge work points
10/06/08-10/10/08
  • Staked 8 Lead along new retaining wall
  • Preparation of crash wall for pouring
  • Staked 7 Lead, 8 Lead & Industrial track East of Cicero
10/27/08-10/31/08
  • Staked 7 Lead, 8 Lead and Industrial track East of the Cicero Bridge
  • Staked underdrain from 56+00 to Cicero Bridge
11/03/08-11/07/08
  • Contractors built 7 Lead track through Cicero Ave. bridge
  • Restaked 8 Lead from 58+00 to east end of site
11/17/08-11/21/08
  • Staked realigned industrial track from 0+00 to 7+05