Browning Engineering Limited
Bellevue Yard
2012
- Located site control with GPS base station
- Ran level circuits to distribute vertical control around site
- Cross-sectioned proposed hump yard area
- Level circuits and pre-construction meeting
- Staked silt fence on South side of project.
- Staked centerline of track 64 from 9+00 to 47+00
- Localized base station on surrounding control points
- Staked pond structures and station left daylight points
- Staked grading limits on South Bypass track from 3+00 to 188+00
- Staked edge of Car Shop Access Road and edge of adjacent ditches from 509+00
to 512+50
- Staked power poles and air lines on existing hump
- Marked North side of electric conduit of the North side of the Car Shop Access Road
- Staked Daylight points of hump
- Began work on South Bypass cross sections
- Staked grading limits on W-4 alignment from 63+00 to 115+00
- Staked wetlands, catch basins and jack/bore pits
- Worked with C&S crews to located all track wire near proposed jack/bore pits
- Staked R1/42 switch for track crew along the car shop ladder
- Staked centerline of RIP track.
- Worked with potholing crew to located C&S wires near bores.
- Staked Class Yard catch basins.
- Located C&S marks near the zone 4 bungalow.
- Staked IN4-4 receiving pit.
- Staked split casings for underground crew.
- Shot existing ground elevations at proposed drill shafts.
- Staked out location for jack/bore machine.
- Located potholed wires with C&S crew
- Located conduit runs near existing group retarders.
- Shot stripping limits of proposed class yard.
- Staked location of new IN5 run.
- Staked offsets of the centerline of track B-2 for proposed road location.
- Cross sectioned along proposed A5 track from 20+00 to 115+00.
- Staked all RIP catch basins, offset and graded catch basins on North side.
- Cross sectioned proposed class yard from 8+00 to 19+00