47th St Intermodal Facility Improvements

  • 11/03/14-11/08/14
  • Cut and throw of main 1 shoofly back into original position, lined
    existing main 2 panels at 14' offset of main 1.
  • Installed track 3 ladder switch.
  • Staked yard air steel casing pipe points and checked existing
    pavement grades for K-Five.  Asbuilt new sewer structure.

  • 10/28/14-10/31/14
  • Graded track 6 with tamper.
  • Asbuilt Pad Expansion yard tracks 6, 7, and 8.
  • Gave edge of tie, lined, and gave grades for track 5A.
  • Mapped existing yard tracks for potential reconfiguration.

  • 10/20/14-10/23/14
  • Gave grades, lined, and mapped main 1 and 2 panels over 51st
    St bridge.
  • Mapped existing tracks for new curve design.
  • Lined track 6 panels.

  • 10/15/14-10/16/14
  • Placed and lined switch for track 6 from track 2.

  • 10/06/14-10/09/14
  • Designed new south alignment for track 6.
  • Measured, graded, and lined track 6 panel.
  • Mapped more existing yard track.
  • Painted out tracks 2-6, 9, and 10.

  • 09/29/14-10/03/14
  • Asbult existing yard track 1.
  • Placed and lined track 6-7 crossover switches.
  • Cut and throw tracks 7 and 8 south of 51st St, measured and
    lined both tracks.
  • Lined panel for track 7.

  • 09/22/14-09/26/14
  • Painted out north infiltration trench for K-Five, graded stone with
    Northwest General Contractors.
  • Set and aligned track 8-7 switch.
  • Painted out C/L for tracks 6, 7, and 8 for visual.

  • 09/15/14-09/19/14
  • Graded CA-6 with K-Five in south of 51st St excavation
  • Asbuilt shooflies
  • Measured points and lengths for future cut and throw of
    shooflies, north and south

  • 09/09/14-09/11/14
  • Measured switches and track lengths for cuts and installation of
    switches.
  • Graded stone for track 10 swing.
  • Installed tracks 9 and 10 switches and their connecting panels,
    graded for tamper.
  • Asbuilt temporary air line locations.

  • 09/02/14-09/04/14
  • Checked and measured McHugh saw cut in temp track 40 and
    41 area.
  • Cut and throw of temp tracks 40 and 41, lined track.

  • 08/25/14-08/28/14
  • Painted temp tracks 40 and 41 and graded area.
  • Checked track 10 excavation grades.
  • Painted out tracks 8 and 9 with switches for visual.
  • Shot and measured tracks in hangar for Mechanical Dept.

  • 08/18/14-08/22/14
  • Graded track 9 from south end to 51st St for tamper.
  • Set nails for saw cut boundary on south end.
  • Checked existing grades for temp track 40.

  • 08/03/14-08/08/14
  • Cut and throw mains 1 and 2 into shooflies, lined and graded
    track.
  • Topo area east of 51st St Bridge.
  • Painted all Pad Expansion tracks in area south of 51st St for
    visual.

  • 07/28/14-08/01/14
  • Measured CA-6 on 51st St Bridge.
  • Measured and marked out saw cut areas for mains 1 and 2 in
    preparation for cut and throw.
  • Lined and raised main 1 and 2 shoofly panels from south end to
    51st St bridge.

  • 07/21/14-07/24/14
  • Spiked and flagged main 1 shoofly panel on south end to 51st
    St bridge, checked top of rail elevations.
  • Lined mains 1 and 2 shoofly panels.
  • Located and shot existing manholes on east end of yard.

  • 07/14/14-07/19/14
  • Shot fabric limits south of 51st St and checked CA-6 and CA-7
    grades.
  • Asbuilt T3 fiberoptic trench.
  • Graded ballast south of 51st St.
  • Lined mains 1 and 2 shoofly panels north of 51st St and graded
    panels for tamper.

  • 07/07/14-07/11/14
  • Cross-sectioned excavation area south of 51st St Bridge.
  • Asbuilt T3 fiberoptic trench.
  • Shot fabric limits and checked CA-6 grades.

  • 06/30/14-07/02/14
  • Graded ballast in excavation north of 51st St.
  • Spiked and flagged edge of tie for shoofly panels.

  • 06/23/14-06/27/14
  • Graded ballast in excavation north of 51st St.
  • Graded entire length new yard track 5 for tamper.
  • Spiked and flagged point of switch and point of frog for switch 4.
  • Mapped and recorded T3 fiberoptic paint markings for future
    excavation.
  • Checked and shot CA-7 and fabric limits.
  • Measured and recorded area north of 51st St still in need of
    fabric and stone.

  • 06/18/14-06/20/14
  • Checked cut in excavation area north of 51st St bridge.
  • Lined yard track 5
  • Checked and shot CA-7 and fabric limits.
  • Staked 12' offset entire length of future yard track 2 for visual.

  • 06/02/14
  • Sprayed 12' offset yard track 2 to denote limits of future
    excavation

  • 05/27/14-05/28/14
  • Asbuilt excavation south of yard track 5.
  • Measured track for 5 cut and throw.
  • Gave center line and graded area for track 5 south of 51st St.

  • 05/18/14-05/23/14
  • Graded yard tracks 6 and 5A for tamper.
  • Asbuilt track 5A, tracks 11 and 12 stubs, west bridge deck.
  • Measured rail space for track 5 panel and tracks 3 and 4 for cut
    and throw to track 5.
  • Checked track 5 excavation south of 51st St.

  • 05/12/14-05/16/14
  • Graded tracks 5A and 6 for tamper.
  • Set and lined new tracks 5A and 6 panels.
  • Cut and throw yard track 2 to track 6 on far north end.
  • Asbuilt tracks 7 and 8.
  • Painted out edge of tie for tracks 5A near hump and 6 in ladder
    for visual.

  • 05/04/14-05/09/14
  • Graded tracks 7 and 8 with tamper.
  • Cut and throw, lined and graded south end of track 6.
  • Asbuilt track 6 after tamping.
  • Asbuilt asphalt area over 51st St bridges.
  • Set and lined switch from 5A to 6.