47th St Intermodal Facility Improvements con't.
- Graded yard tracks 6, 7, and 8 for tamper.
- Graded ballast with E&L for tracks 5A and 6.
- Staked point of switch and point of frog for 5A and 6 switch.
- Graded ballast with E&L for tracks 4, 5, and 5A.
- Set and lined switch for track 7 to 6.
- Painted C/L for tracks 5 and 5A for visual.
- Topo'd hump area and toes of slope on north end.
- Shot and measured CA-7 perimeter for north excavation.
- Graded ballast for entirety of track 6 and gave edge of tie.
- Lined west rail of track 6.
- Shot fabric limits and checked grades for CA-7 in north
excavation.
- Measured, graded, and lined tracks 9 and 10 panels over 51st
St bridge.
- Measured and determined track lengths needed for panels to
construct tracks 6, 5, and 5A.
- Lined track 7 from south match point to 51st St.
- Cross-sectioned McHugh excavation.
- Staked offsets and graded length of track 6 from beginning to
end.
- Lined portions of track 7 and 8.
- Shot cross-sections and checked McHugh excavation grades.
- Gave grade and offsets for track 8 panel over 51st St bridge.
- Checked McHugh grades and monitored undercut excavation.
- Cross-sectioned new excavation for track 8 north of 51st St.
- Gave grade for track 8 for tamper.
- Set and lined track 10 to 8 switch.
- Lined track 7 panels.
- Checked depth of trench and alignment of 5A.
- Checked McHugh grades for north excavation.
- Painted out C/L for track 8 and aligned track 8 panel.
- Painted out track 8 future grades for tamper.
- Cross-sectioned tracks 7 and 8 area.
- Measured depth of sand in potholes.
- Set and aligned track 9 to 8 switch.
- Staked existing catch basins and recorded locations.
- Graded ballast in new switch area.
- Gave grades for track 7 and 8 cut area and cross-sectioned
same area.
- Sprayed C/L for tracks 6 and 5A for visual.
- Shot new control for Benesch surveyors.
- Gave grades for McHugh in track 7 and 8 cut area.
- Staked and checked match points at north end of job site
- Mapped and measured McHugh saw cut for track 8.
- Painted out 108' offset future track 2 station 30+00 to 39+00.
- Painted out C/L tracks 6 and 8 on north end of job site.
- Painted out ladder points of switches.
- Asbuilt tracks P38-P41 area.
- Staked track 9, 8, and 7 switches on north end of site.
- Painted out saw cut line for track 8 and C/L track 8.
- Checked top of rail for existing tracks for future planning.
- Gave area of excavation to McHugh.