B-C Concourse
Current plans dated: 03/06/2009
- 5/11/09-5/15-09: Staked proposed excavation limits for phases 1-4
- 5/18/09-5/22/09: Mapped existing conditions in phases 1-4
- 6/22/09-6/26/09: Began sawcutting and excavation on Phase 1
- 7/06/09-7/11/09: Poured sleeper slab on Phase 1
- 7/13/09-7/17/09: Poured 18" Reinforced Concrete on Phase 1
- 7/27/09-7/3109: Prepared 18"-24" area for pouring
- 8/03/09-8/07/09: Excavate and pour sleeper slab in temporary service road area
- 8/10/09-8/14/09: Worked on Phase 1 asbuilt. Staked limits and temporary striping
for phase 2.
- 8/17/09-8/21/09: Poured sleeper slab and prepared for 18" PCC Pouring
- 8/31/09-9/04/09: Finished pouring concrete on Phase 2, layout of limits for Phase 3
- 9/14/09-9/18/09: Saw cuts and excavation of phase 3.
- 9/21/09-9/25/09: Poured phase 3 sleeper slab and prepared for additional 18" PCC
pouring.
- 10/05/09-10/09/09: Saw cuts and excavation on Phase 4.
- 10/19/09-10/23/09: Poured sleeper slab and 18" reinforced concrete.
- 10/26/09-10/30/09: Poured extra concrete area, 18-24" area.
- 11/02/09-11/06/09: Excavated temporary service road, finished pouring sleeper slab
- 11/09/09-11/13/09: Site cleanup, striping of Phase 4.
Browning Engineering Limited